<img height="1" width="1" style="display:none" src="https://www.facebook.com/tr?id=259345994497019&amp;ev=PageView&amp;noscript=1">
SELECT A LOCATION

October 2020: Project Update

by Spooky Nook Sports on October 8, 2020

Spooky Nook Sports Champion Mill project in Hamilton, Ohio. Project update for October 2020.

Spooky Nook Sports Complex (Mill 1)

WORK COMPLETED IN THE PAST 2 WEEKS:

  • Continue laying walls in Building 200 and 300
  • Install grease tanks and piping at Building 200 location.
  • Continue piping in Building 500 Shower/Locker Room areas.

TWO-WEEK LOOK AHEAD:

  • Grading at South area of Site for Service road and Parking lot.
  • Erecting Building 400 columns, beams and joist.
  • Laying interior masonry wall at Climbing wall area of Building 400.

LOOKING WEST – MASONRY PROGRESSMasonry progress.

LOOKING WEST- BUILDING 100, EAST

Building 100 progress.

LOOKING SOUTH EAST– BUILDING 400

Installing roof rafters.

Spooky Nook Hotel and Conference Center (Mill 2)

WORK COMPLETED IN THE PAST 2 WEEKS:

  • Demolish wood floor at third floor of shear wall.
  • Installation of walls on elevator 3/4 and 4/5.
  • Continue roof installation on Building E.

TWO-WEEK LOOK AHEAD:

  • Forming and pouring curbs at exterior storefront openings.
  • Helicopter to remove equipment off Mill 2 roof.
  • Brick replacement and pointing of interior side of exterior walls.

LOOKING SOUTHEAST – INSTALLATION OF ELEVATOR 2 3 SECTOR 1

Installation of elevator 2/3.

LOOKING NORTH – FRAMING AROUND THE CRANE MONITOR

Framing around the crane monitor.

LOOKING NORTH – DEMOLITION OF WOOD FLOOR 2ND FLOOR SECTOR 2

Demolition of wood floor.

 

Recent Posts