<img height="1" width="1" style="display:none" src="https://www.facebook.com/tr?id=259345994497019&amp;ev=PageView&amp;noscript=1">

Summer Camps

Read More X

Summer Camps

Read More X
Calendar
Contact

March 2021: Project Update

Published
03/23/2021

Spooky Nook Sports Champion Mill project in Hamilton, Ohio. Project update for March 2021.

Spooky Nook Sports Complex (Mill 1)

WORK COMPLETED IN THE PAST 2 WEEKS:

  • Performing saw cuts for piping in Kitchen/Concession areas Building 100.
  • Installing sprinkler piping mains and branches in Building 100 East section.
  • Completing installation of rod bracing at North end of Building 300.

TWO-WEEK LOOK AHEAD:

  • Setting Roof Curbs on Building 100 as roofing areas are complete.
  • Installing underground piping in Retail/Bakery areas.
  • Laying wall at Centerline of Building 300 North end.

LIFTING AND BRACING LINE 19

Lifting and bracing line 19.

CENTERLINE MASONRY WALL LOOKING WEST FROM EAST SIDE OF THE WALL

Centerline Masonry Wall, looking west from east side.

RE-ROOFING PROGRESS

Re-roofing progress, tapered insulation installation.

Spooky Nook Hotel and Conference Center (Mill 2)

WORK COMPLETED IN THE PAST 2 WEEKS:

  • Hang drywall in Sector 3 on 1st floor.
  • Pouring topping in Sector 3 hotel lobby area North to tenant space.
  • Installed exhaust & make up air duct in Sector 4.

TWO-WEEK LOOK AHEAD:

  • Sprinkler piping in Sector 2 on the 1st floor.
  • Completing grinding on Sector 4 West side on the 2nd floor.
  • Data and electric rough-in on Sector 4 1st floor hotel rooms.

DRYWALL INSTALLATION, HOTEL ROOMS 1ST FLOOR - SECTOR 3Installation of the drywall in the hotel.

INSTALLATION OF METAL DECK FOR THE - 3RD FLOOR- SECTOR 2

Installation of the metal deck for the 3rd floor.

INSTALLATION OF SHOWER STALLS - 1ST FLOOR

Installation of the shower stalls on the 1st floor.

Subscribe to our Blog!

Stay up to date with the latest news from SpookyNook Sports Champion Mill!