March 2021: Project Update

Written by Spooky Nook Sports | Mar 23, 2021 1:46:18 PM

Spooky Nook Sports Champion Mill project in Hamilton, Ohio. Project update for March 2021.

Spooky Nook Sports Complex (Mill 1)

WORK COMPLETED IN THE PAST 2 WEEKS:

  • Performing saw cuts for piping in Kitchen/Concession areas Building 100.
  • Installing sprinkler piping mains and branches in Building 100 East section.
  • Completing installation of rod bracing at North end of Building 300.

TWO-WEEK LOOK AHEAD:

  • Setting Roof Curbs on Building 100 as roofing areas are complete.
  • Installing underground piping in Retail/Bakery areas.
  • Laying wall at Centerline of Building 300 North end.

Lifting and bracing line 19.

Centerline Masonry Wall, looking west from east side.

Re-roofing progress, tapered insulation installation.

Spooky Nook Hotel and Conference Center (Mill 2)

WORK COMPLETED IN THE PAST 2 WEEKS:

  • Hang drywall in Sector 3 on 1st floor.
  • Pouring topping in Sector 3 hotel lobby area North to tenant space.
  • Installed exhaust & make up air duct in Sector 4.

TWO-WEEK LOOK AHEAD:

  • Sprinkler piping in Sector 2 on the 1st floor.
  • Completing grinding on Sector 4 West side on the 2nd floor.
  • Data and electric rough-in on Sector 4 1st floor hotel rooms.

Installation of the drywall in the hotel.

Installation of the metal deck for the 3rd floor.

Installation of the shower stalls on the 1st floor.