Spooky Nook Sports Champion Mill project in Hamilton, Ohio. Project update for March 2021.
Spooky Nook Sports Complex (Mill 1)
WORK COMPLETED IN THE PAST 2 WEEKS:
- Performing saw cuts for piping in Kitchen/Concession areas Building 100.
- Installing sprinkler piping mains and branches in Building 100 East section.
- Completing installation of rod bracing at North end of Building 300.
TWO-WEEK LOOK AHEAD:
- Setting Roof Curbs on Building 100 as roofing areas are complete.
- Installing underground piping in Retail/Bakery areas.
- Laying wall at Centerline of Building 300 North end.
Lifting and bracing line 19.
Centerline Masonry Wall, looking west from east side.
Re-roofing progress, tapered insulation installation.
Spooky Nook Hotel and Conference Center (Mill 2)
WORK COMPLETED IN THE PAST 2 WEEKS:
- Hang drywall in Sector 3 on 1st floor.
- Pouring topping in Sector 3 hotel lobby area North to tenant space.
- Installed exhaust & make up air duct in Sector 4.
TWO-WEEK LOOK AHEAD:
- Sprinkler piping in Sector 2 on the 1st floor.
- Completing grinding on Sector 4 West side on the 2nd floor.
- Data and electric rough-in on Sector 4 1st floor hotel rooms.
Installation of the drywall in the hotel.
Installation of the metal deck for the 3rd floor.
Installation of the shower stalls on the 1st floor.