Spooky Nook Sports Complex (Mill 1)

WORK COMPLETED IN THE PAST 2 WEEKS:

  • Complete crushing and clean up at South end of the site.
  • Continue forming for concrete walls.
  • Continue steel erection at Building 300.

TWO-WEEK LOOK AHEAD:

  • Complete removal of South interior section of existing building façade.
  • Begin laying interior masonry walls in Building 100.
  • Mobilize Crane to site for setting of PEMB steel girders.

CONCRETE FORMS WITH SNAP-TIES BEING PREPARED

B STREET FAÇADE BEING SUPPORTED BY THE REMAINING STEEL STRUCTURE FOR SAFETY

BUILDING 300’S MAIN ROOF GIRDER SECTIONS BEING PREASSEMBLED ON THE CONCRETE SLAB

Spooky Nook Hotel and Conference Center (Mill 2)

WORK COMPLETED IN THE PAST 2 WEEKS:

  • Salvaging glass block from the exterior windows of Building 1.
  • Saw cutting and core drilling for underground plumbing in Sector 4.
  • Beginning the replacement of glass block at the interior windows in Sector 1.

TWO-WEEK LOOK AHEAD:

  • Complete removal of concrete floor for 2nd floor stairwell.
  • Complete dismantling and removal of overhead crane from the 2nd floor.
  • Continue saw cutting and core drilling for underground plumbing in Sectors 3 and 4.

SALVAGED GLASS BLOCK FROM BUILDING A’S EXTERIOR FAÇADE

USING OXYACETYLENE TORCH TO CUT ONE OF THE TWO BRIDGE BEAMS

BRIDGE BEAM SITTING ON THE FLOOR WAITING TO BE CUT INTO SECTIONS