Spooky Nook Sports Champion Mill project in Hamilton, Ohio. Project update for January 2022.
Spooky Nook Sports Complex (Mill 1)
WORK COMPLETED IN THE PAST 4 WEEKS:
- Installed sprinkler piping in the south area of building 400 under the Mezzanine.
- Installed remaining block walls in the Kitchen and Concession areas.
- Completed installation of sleeves through roof curbs on building 300.
TWO-WEEK LOOK AHEAD:
- Installing and grading topsoil along service drive and parking lot 3 areas.
- Installing store front window frames at Building 400.
- Installing decking on Mezzanine area in Building 100.
Progress of window installation along B Street.
Progress of the Mezzanine in Building 400.
Prepping walls in Building 200 for final finish.
Spooky Nook Hotel and Conference Center (Mill 2)
WORK COMPLETED IN THE PAST 2 WEEKS:
- Installed coating on exterior concrete features on the east side of the building.
- Priming and body coat in sectors 3 and 4 of the hotel rooms.
- Installed arcade walls on the second and third floors.
TWO-WEEK LOOK AHEAD:
- Finish painting in west side hotel rooms on the first floor.
- Pouring concrete for sidewalks on west side.
- Caulking and painting window trim in hotel rooms.
Installation of windows in Grand Ballroom on 2nd floor.
Installation of grand staircase.
Sidewalk implementation on the north end of the building.