Champion Mill Blog

January 2022: Project Update

Written by Spooky Nook Sports | Jan 12, 2022 3:57:57 PM

Spooky Nook Sports Champion Mill project in Hamilton, Ohio. Project update for January 2022.

Spooky Nook Sports Complex (Mill 1)

WORK COMPLETED IN THE PAST 4 WEEKS:

  • Installed sprinkler piping in the south area of building 400 under the Mezzanine.
  • Installed remaining block walls in the Kitchen and Concession areas.
  • Completed installation of sleeves through roof curbs on building 300.

TWO-WEEK LOOK AHEAD:

  • Installing and grading topsoil along service drive and parking lot 3 areas.
  • Installing store front window frames at Building 400.
  • Installing decking on Mezzanine area in Building 100.

Progress of window installation along B Street.

Progress of the Mezzanine in Building 400.

Prepping walls in Building 200 for final finish.

Spooky Nook Hotel and Conference Center (Mill 2)

WORK COMPLETED IN THE PAST 2 WEEKS:

  • Installed coating on exterior concrete features on the east side of the building.
  • Priming and body coat in sectors 3 and 4 of the hotel rooms.
  • Installed arcade walls on the second and third floors.

TWO-WEEK LOOK AHEAD:

  • Finish painting in west side hotel rooms on the first floor.
  • Pouring concrete for sidewalks on west side.
  • Caulking and painting window trim in hotel rooms.

Installation of windows in Grand Ballroom on 2nd floor.

Installation of grand staircase.

Sidewalk implementation on the north end of the building.