Champion Mill Blog

January 2021: Project Update

Written by Spooky Nook Sports | Jan 5, 2021 9:31:15 PM

Spooky Nook Sports Champion Mill project in Hamilton, Ohio. Project update for January 2021.

Spooky Nook Sports Complex (Mill 1)

WORK COMPLETED IN THE PAST 2 WEEKS:

  • Continuing installation of the roof drains and storm piping in Building 100.
  • Completed rework of Door opening 300U center wall Building 300.
  • Begin to install piping in old elevator shaft in Building 200.

TWO-WEEK LOOK AHEAD:

  • Setting Clearspan trusses at the south end of Building 300 to complete the steel erection.
  • Completed walls at new entry location Building 100 center.
  • Excavating and installing downspout leaders at West side of Building 500.

Building 100 roofing/re-roofing progress.

Door frame installation.

Fire protection feed main piping in old elevator shaft.

Spooky Nook Hotel and Conference Center (Mill 2)

WORK COMPLETED IN THE PAST 2 WEEKS:

  • Laid brick windowsills in Sector 3 & 4.
  • Set equipment and running piping in South mechanical room.
  • Installed blocking & drywall top out in Sector 3 1st floor.

TWO-WEEK LOOK AHEAD:

  • Pouring sand cement leveler around & between geofoam.
  • Installing roof steel at new HVAC curbs in Sector 2 & 3.
  • Installing ductwork for exhaust & make up air in Sector 3 hotel rooms.

Closing off exiting masonry openings.

Installation of concrete topping - 2nd floor.

Installation of geothermal piping into mechanical room.