Spooky Nook Sports Champion Mill project in Hamilton, Ohio. Project update for January 2021.
Spooky Nook Sports Complex (Mill 1)
WORK COMPLETED IN THE PAST 2 WEEKS:
- Continuing installation of the roof drains and storm piping in Building 100.
- Completed rework of Door opening 300U center wall Building 300.
- Begin to install piping in old elevator shaft in Building 200.
TWO-WEEK LOOK AHEAD:
- Setting Clearspan trusses at the south end of Building 300 to complete the steel erection.
- Completed walls at new entry location Building 100 center.
- Excavating and installing downspout leaders at West side of Building 500.
Building 100 roofing/re-roofing progress.
Door frame installation.
Fire protection feed main piping in old elevator shaft.
Spooky Nook Hotel and Conference Center (Mill 2)
WORK COMPLETED IN THE PAST 2 WEEKS:
- Laid brick windowsills in Sector 3 & 4.
- Set equipment and running piping in South mechanical room.
- Installed blocking & drywall top out in Sector 3 1st floor.
TWO-WEEK LOOK AHEAD:
- Pouring sand cement leveler around & between geofoam.
- Installing roof steel at new HVAC curbs in Sector 2 & 3.
- Installing ductwork for exhaust & make up air in Sector 3 hotel rooms.
Closing off exiting masonry openings.
Installation of concrete topping - 2nd floor.
Installation of geothermal piping into mechanical room.