December 2020: Project Update

Written by Spooky Nook Sports | Dec 8, 2020 5:10:30 PM

Spooky Nook Sports Champion Mill project in Hamilton, Ohio. Project update for December 2020.

Spooky Nook Sports Complex (Mill 1)

WORK COMPLETED IN THE PAST 2 WEEKS:

  • Completed rough grading and compaction of the outdoor soccer field.
  • Begin the work to plumb, square and brace the steel of Building 300.
  • Staging to install storm line and structures along north side of Rhea Street.

TWO-WEEK LOOK AHEAD:

  • Installing Downspout leaders along West side of Building 300.
  • Began installing hangers for the roof drains and storm piping in Building 100.
  • Installing temporary lighting as areas are closed in.

Steel erection progress in corridor.

Building Line 22 & 23 straightened and ready for bracing.

Workers installing storm piping and hangers.

Spooky Nook Hotel and Conference Center (Mill 2)

WORK COMPLETED IN THE PAST 2 WEEKS:

  • Re-roof on Building D.
  • Installation of deck angle for new third floor in Sector 3 & 4.
  • Temporary closures at door & window openings.

TWO-WEEK LOOK AHEAD:

  • Install hydronic piping in Sector 4.
  • Installing sprinkler main in Sector 3 and 4 for the 3rd floor.
  • Continue to install metal stud walls for hotel rooms in Sector 3 East and West side.

Installation of new roof.

Installation of temporary foam in window openings.

Installation of metal stud walls in hotel rooms.