Spooky Nook Sports Champion Mill project in Hamilton, Ohio. Project update for December 2020.
Spooky Nook Sports Complex (Mill 1)
WORK COMPLETED IN THE PAST 2 WEEKS:
- Completed rough grading and compaction of the outdoor soccer field.
- Begin the work to plumb, square and brace the steel of Building 300.
- Staging to install storm line and structures along north side of Rhea Street.
TWO-WEEK LOOK AHEAD:
- Installing Downspout leaders along West side of Building 300.
- Began installing hangers for the roof drains and storm piping in Building 100.
- Installing temporary lighting as areas are closed in.
Steel erection progress in corridor.
Building Line 22 & 23 straightened and ready for bracing.
Workers installing storm piping and hangers.
Spooky Nook Hotel and Conference Center (Mill 2)
WORK COMPLETED IN THE PAST 2 WEEKS:
- Re-roof on Building D.
- Installation of deck angle for new third floor in Sector 3 & 4.
- Temporary closures at door & window openings.
TWO-WEEK LOOK AHEAD:
- Install hydronic piping in Sector 4.
- Installing sprinkler main in Sector 3 and 4 for the 3rd floor.
- Continue to install metal stud walls for hotel rooms in Sector 3 East and West side.
Installation of new roof.
Installation of temporary foam in window openings.
Installation of metal stud walls in hotel rooms.