WORK COMPLETED IN THE PAST 2 WEEKS:

  • Removal of concrete slab sections in advance of foundation operations. Concrete slab sections removed are being ground into usable aggregate.
  • Survey control for foundation layout.
  • Forming and pouring underpinning and footings.

TWO-WEEK LOOK AHEAD:

  • Continue to remove and grind concrete pad sections for foundations.
  • Continue excavation and pouring of foundations.
  • Start rough grading at South end of site.
  • Begin restoration of exterior brick, lintels and concrete windowsills.

Tying reinforcing mats on concrete slab.

 

Breaking up concrete slab at footing locations.

 

Pouring flowable fill (lean concrete) as underpinning.